Sl No |
div |
Name of the work |
Est
Cost
|
AS
date
|
TS
date
|
Tender
date
|
work order
date
|
Exp. |
Probable dated of completion |
Stage of work |
| 2007-08 |
| 1 |
12 |
Construction of Additional class room at Manakkadu Corporation girls Hr.sec. School |
24.00 |
31.10.07 |
31.10.07 |
4.6.08 |
17.7.08 |
|
31.7.09 |
Basement progress |
| 2 |
32 |
Repairs and maintenance of Car street Corporation Ele. School |
5.00 |
7.5.07 |
23.8.07 |
28.8.08 |
15.10.07 |
|
31.5.09 |
Roof level |
| 3 |
41 |
Repairs and maintenance of Pavadi Corporation Ele. School |
6.50 |
7.5.07 |
23.8.07 |
28.8.08 |
20.11.07 |
|
31.7.09 |
Dismantling work in progress |
| 2008-09 |
| 4 |
31 |
Construction of Mid-Day meals kitchen room students cycle shed Students Dinning shed,staffs cycle shed and open Auditorium stage at Kottai Boys Hr.sec. school |
9.90 |
30.4.08 |
9.5.08 |
30.10.08 |
2.12.08 |
|
31.7.09 |
Basement progress |
| 5 |
31 |
Construction of grand Floor and first floor additional class room building at kottai Boys Hr, Sec, school |
20.00 |
30.4.08 |
9.5.08 |
30.10.08 |
2.12.08 |
|
31.7.09 |
Basement progress |
| 6 |
31 |
Construction of Toilet Block and Urinals Block at Kottai Boys Hr.Sec. School |
9.90 |
30.4.08 |
9.5.08 |
30.10.08 |
2.12.08 |
|
31.7.09 |
Basement progress |
| 7 |
31 |
Construction of ditional class room Building to the First Floor of East side main Building at Kottai Boys Hr.Sec. School |
4.00 |
19.3.08 |
9.5.08 |
30.10.08 |
2.12.08 |
|
31.5.09 |
Roof laid |
| 8 |
31 |
Construction of additional class room Building Administrative Building Science Lab, and Auditorium Hall at Kottai Boys Hr.Sec. School |
86.00
|
|
|
|
|
|
|
A.S for DMA |
| 9 |
31 |
Construction of comound wall at Kottai Boys Hr.Sec. School |
8.00 |
30.4.08 |
9.5.08 |
30.10.08 |
2.12.08 |
|
31.7.09 |
Brick work in progress |
| 10 |
8 |
Construction of comound wall and repairs to the class room Building at corporation Elementary school in chinnathurupathy |
12.60 |
28.06.08 |
30.06.08 |
6.1.09 |
27.2.09 |
|
31.8.09 |
Earth work in progress |
| 11 |
32 |
Repairs and maintenance of compound wall at river side road Corporation School |
5.00 |
3.4.08 |
05.05.08 |
4th call Tender not reieved |
|
|
|
Tender to be called |
| 12 |
32 |
Reæirs and maintance of compound wall at river side road Corporation Building |
14.20 |
30.06.08 |
05.05.08 |
28.05.08 |
4.7.08 |
|
31.8.09 |
Brick work in progress |
| 13 |
15 |
Construction of compound wall at Corporation Elementary Shool at Ram nagar |
10.75 |
30.6.08 |
9.6.08 |
25.7.08 |
4.9.08 |
|
15.5.09 |
White wash in progress |
| 14 |
46 |
Providing paver block for ground at Gugai Girls higher secondary School |
8.30 |
30.7.08 |
21.7.08 |
25.9.08 Tender not reieved |
|
|
|
Tender to be called |
| 15 |
46 |
Construction of Toilet at Gugai Girls higher secondary School |
5.10 |
30.7.08 |
8.8.08 |
3rd call Tender not reieved |
|
|
|
Tender to be called |
| 16 |
10 |
Construction of toilet with water supply arrangemets at Puttu Mariyamman Middle School |
5.20 |
30.9.08 |
6.10.08 |
7.11.08 |
10.12.08 |
|
31.7.09 |
Earth work in progress |
| 17 |
46 |
Repairs and Maintenance of class room at Gugai girls higher Secondary School |
7.00 |
30.9.08 |
22.10.08 |
5.12.08 |
9.1.09 |
|
31.7.09 |
Work to be started |
| 18 |
49 |
Construction of toilet blick to the Corporation Ele. School at nethimedu |
6.40 |
20.8.08 |
22.10.08 |
5.12.08 |
22.1.09 |
|
31.7.09 |
Earth work in progress |
| 19 |
49 |
Constuction of Children toilet at Annathanapatty Middle School |
5.60 |
20.8.08 |
22.10.08 |
6.1.09 |
|
|
|
Tender received |
| 20 |
43 |
Construction of toilet urinals with water supply arrangements and maintenance of School building at No. 1 New street Hr.Sec. School |
5.00 |
17.9.08 |
22.11.08 |
3.3.09 2nd call, Tender not received |
|
|
|
Tender to be called |
| 21 |
20 |
Construction of School building at Corporation Middle School at Old Suramangalam |
16.80 |
12.11.08 |
4.12.08 |
3.3.09 Tender received |
|
|
|
Tender received on 3.03.2009. |
| 22 |
2 |
Construction of compound wall and providing Paver block to the Corporation School at Chinnammapalaiyam |
5.70 |
3.12.08 |
4.12.08 |
3.3.09 Tender not received |
|
|
|
Tender received on 03.03.2009. |
| 23 |
33 |
Construction of compound wall at Corporation Shool at Market Street. |
3.00 |
26.12.08 |
29.12.08 |
3.3.09 Tender received |
|
|
|
Tender received on 03.03.2009. |
| 24 |
42 |
Construction of additional class room Building in 1st floor of pavadi girls Hr.Sec. School ( Branch ) at narayana nagar 3rd cross |
21.30 |
27.2.09 |
27.2.09 |
18.3.09 Tender received |
|
|
|
Tender received on 18.03.2009. |
| 25 |
12 |
Laying of Lotta stone ( Flooring ) Corporation Kamaraj Girls Hr.Sec. School at Manakadu |
14.50 |
27.2.09 |
27.2.09 |
Tender to be called |
|
|
|
Tender to be called |
| 26 |
22 |
Construction of additional class room at Sivathapuram Corporation School |
24.50 |
12.11.08 |
4.12.08 |
18.3.09 Tender received |
|
|
|
Tender received on 18.03.2009 |